Home > Download > SMU - Question Paper
> MCA > MC0084
Software Project Management & Quality Assurance
This is the collection of
Sikkim Manipal University (SMU) question and answers for Software Project Management & Quality Assurance. It will help
to prepare your examination. All question paper are
classified as per semester, subject code and question type of Part A, Part B and Part C with
multiple
choice options
as same as actual examination. SMU question papers includes
year 2024, 2023, 2022 Sem I, II, III, IV, V, VI examinations
of all subjects.
SMU question test set of old,
last and previous year are updated
regularly and it is absolutely free to use. Question paper includes Visual basic 6, VB.Net, C#, ASP.Net,
Web, Oracle, Database, SQL, Software Engineering, C, C++, OOPS, MBA, MCA, BSC IT I have requested
you kindly send me the question paper of Software Project Management & Quality Assurance, SMU - Master of Computer Application.
Course Name
MCA (Master of Computer Application)
Subject Code MC0084 (Software Project Management & Quality Assurance)
Get Questions
PART - A
PART - B
PART - C
Subject : Software Project Management & Quality Assurance
MC0084 : PART - B
Q. 1 | External interface requirements used to specify ____ |
| A) | Interaction with the user, hardware and
software |
| B) | Data flow from software to hardware | | C) | Attributes of entities | | D) | None of the above | | | | Q. 2 | ____ type of model is used where the requirement is hard to determine 1. Water fall 2. Prototype 3. Enhancement 4. Spiral Model |
| A) | 1, 2, 3 |
| B) | 1, 4 | | C) | 3, 4 | | D) | All of the above | | | | Q. 3 | Match the Software Project terms Task set selector value 1. TSS< 1 2 2. 1.03. TSS>2.4 Degree of rigor i. Strict ii. Structured iii. Casual |
| A) | 1 – i, 2 – ii, 3 – iii |
| B) | 1 – ii, 2 – i, 3 – iii | | C) | 1 – ii, 2 – iii, 3 – I | | D) | 1 – iii, 2 – ii, 3 – I | | | | Q. 4 | Based on the data. ar. Estimation model off the form id represented in the ____ Equation |
| A) | E=[LOC x B 0.333 P]3 x (1.t4) |
| B) | E=[LOC x B 0.333 P]3 x (1/t4) | | C) | E=[LOC x B 0.333/P]3 x (1/t4) | | D) | E=[LOC x B 0.333/P]3 x (1.t4) | | | | Q. 5 | In Software Project New Object Points is calculated using ____ equation |
| A) | NOP=(Object Points) x [(100-%reuse)/200] |
| B) | NOP=(Object Points) x [(100-%reuse)/50] | | C) | NOP=(Object Points) x [(50-%reuse)/25] | | D) | None of the above | | | |