P2Pprogrammer 2 programmer

Home > Download > SMU - Question Paper > MCA > MC0084

Software Project Management & Quality Assurance


This is the collection of Sikkim Manipal University (SMU) question and answers for Software Project Management & Quality Assurance. It will help to prepare your examination. All question paper are classified as per semester, subject code and question type of Part A, Part B and Part C with multiple choice options as same as actual examination. SMU question papers includes year 2024, 2023, 2022 Sem I, II, III, IV, V, VI examinations of all subjects.

SMU question test set of old, last and previous year are updated regularly and it is absolutely free to use. Question paper includes Visual basic 6, VB.Net, C#, ASP.Net, Web, Oracle, Database, SQL, Software Engineering, C, C++, OOPS, MBA, MCA, BSC IT I have requested you kindly send me the question paper of Software Project Management & Quality Assurance, SMU - Master of Computer Application.

Course Name        MCA (Master of Computer Application)

Subject Code       MC0084 (Software Project Management & Quality Assurance)

Get Questions        PART - A    PART - B    PART - C

Subject : Software Project Management & Quality Assurance

     MC0084 : PART - B    


Q. 1External interface requirements used to
specify ____
 A)Interaction with the user, hardware and software
 B)Data flow from software to hardware
 C)Attributes of entities
 D)None of the above
   
Q. 2 ____ type of model is used where the
requirement is hard to determine
1. Water fall
2. Prototype
3. Enhancement
4. Spiral Model
 A)1, 2, 3
 B)1, 4
 C)3, 4
 D)All of the above
   
Q. 3Match the Software Project terms
Task set selector value
1. TSS< 1 2
2. 1.03. TSS>2.4
Degree of rigor
i. Strict
ii. Structured
iii. Casual
 A)1 – i, 2 – ii, 3 – iii
 B)1 – ii, 2 – i, 3 – iii
 C)1 – ii, 2 – iii, 3 – I
 D)1 – iii, 2 – ii, 3 – I
   
Q. 4Based on the data. ar. Estimation model off
the form id represented in the ____ Equation
 A)E=[LOC x B 0.333 P]3 x (1.t4)
 B)E=[LOC x B 0.333 P]3 x (1/t4)
 C)E=[LOC x B 0.333/P]3 x (1/t4)
 D)E=[LOC x B 0.333/P]3 x (1.t4)
   
Q. 5In Software Project New Object Points is
calculated using ____ equation
 A)NOP=(Object Points) x [(100-%reuse)/200]
 B)NOP=(Object Points) x [(100-%reuse)/50]
 C)NOP=(Object Points) x [(50-%reuse)/25]
 D)None of the above
   
Click here to get Software Project Management & Quality Assurance (MC0084) New Question


Home > Download > SMU - Question Paper > MCA > MC0084